Applying for a Low-Impact Exploration Licence in NSW – Key Considerations for Applicants

  Section 32B of the Mining Act 1992 (NSW) establishes a special class of exploration licence known as a Low-Impact Exploration Licence (LIEL). Applicants may elect to pursue a LIEL as an alternative pathway to address native title considerations. However, this option comes with notable limitations. Extended Timeframe for Grant Before a LIEL can be granted or renewed, NSW Resources must serve notice on the following representative bodies: Registered native title bodies corporate for the application area Registered native title claimants NTSCORP Limited Under clause 17 of the Mining Regulation 2016 , a LIEL cannot be granted until four months after service of the notice. By contrast, a standard exploration licence is typically processed within 51 business days under NSW Resources’ service delivery standard. Restricted Exploration Activities While a LIEL permits prospecting in areas where native title exists, is presumed to exist, or has not been extinguished, the licence stri...

When Consent Is Not Required: Development on Crown Reserves

  Under clause 23 of the Environmental Planning and Assessment Regulation 2021 (NSW), a development application ordinarily requires the written consent of the landowner. For proposals on Crown land, the relevant landowner is the Minister administering the Crown Land Management Act 2016 (NSW) (“ CLMA ”). The Department of Planning, Housing and Infrastructure – Crown Lands (“ Crown Lands ”) exercises delegated authority to grant the Minister’s consent. Consent is provided only where Crown Lands are satisfied that the proposal aligns with the statutory framework for Crown land management under the CLMA. Applicants typically must lodge a formal request for landowner’s consent, accompanied by the prescribed fee. The assessment process varies in duration depending on the complexity and potential impacts of the proposal, and Crown Lands does not commit to a fixed timeframe for determination. Legislative Change: Crown Land Management Amendment Regulation 2024 The Crown Land Management...

Operating a Quarry in Victoria: Work Authority & Work Plan

  In Victoria’s extractive (quarry) industry, a licence is referred to as a work authority . A work authority is the type of tenement required before commencing quarry operations. Legislative Requirements Under section 77I of the Mineral Resources (Sustainable Development) Act 1990 (Vic) ( MRSDA ), the Minister must not grant a work authority unless satisfied that the applicant has: An approved work plan under s77I; Entered into a rehabilitation bond under s80; Complied with relevant planning schemes and obtained necessary planning permits; Secured all required consents and authorities under the MRSDA or other legislation; and In the case of Crown land, obtained consent from the Crown land Minister. The work plan is the most critical document. Without Ministerial approval of the work plan, an application for a work authority cannot proceed to grant. Work Plan Requirements Under section 77G of the MRSDA, a work plan must be lodged with the Minister unless the proposed extractiv...