Applying for a Low-Impact Exploration Licence in NSW – Key Considerations for Applicants
Section 32B of the Mining Act 1992 (NSW) establishes a special class of exploration licence known as a Low-Impact Exploration Licence (LIEL).
Applicants may elect to pursue a LIEL as an alternative pathway to address native title considerations. However, this option comes with notable limitations.
Extended Timeframe for Grant
Before a LIEL can be granted or renewed, NSW Resources must serve notice on the following representative bodies:
- Registered native title bodies corporate for the application area
- Registered native title claimants
- NTSCORP Limited
Under clause 17 of the Mining Regulation 2016, a LIEL cannot be granted until four months after service of the notice. By contrast, a standard exploration licence is typically processed within 51 business days under NSW Resources’ service delivery standard.
Restricted Exploration Activities
While a LIEL permits prospecting in areas where native title exists, is presumed to exist, or has not been extinguished, the licence strictly limits the scope of authorised activities.
Permitted operations include:
- Aerial surveys
- Geological and surveying field work without clearing
- Sampling by hand methods
- Ground-based geophysical surveys without clearing
- Drilling and associated activities where only minimal clearing is required to establish a drill site
- Environmental field work without clearing
Any activities outside this scope require conversion of the LIEL to a standard exploration licence (EL).
Assessable prospecting operations may be undertaken under a LIEL—often as a complying exploration activity (CEA)—but applications are subject to heightened scrutiny to ensure compliance with low-impact criteria.
Access Arrangements Still Required
Under the Mining Act, native title parties are deemed landholders. Accordingly, a written access arrangement between the LIEL holder and each registered native title body corporate or claimant must be in place before commencing any ground-disturbing activities.
Section 32F further clarifies that this requirement does not replace the need for access arrangements with other landholders, such as Crown Lands or agencies controlling Crown land.
If a LIEL is later converted to a standard EL, existing access arrangements with both native title and non-native title parties must be substantially revised—or new arrangements negotiated—potentially causing costly delays and administrative burdens.
Conclusion
Explorers should carefully assess whether their objectives are better served by a standard EL before applying for a LIEL. While a LIEL provides a pathway to prospect in areas subject to native title, it prohibits advanced exploration activities. Conversion to a standard EL is required before such activities can proceed, and this process carries significant implications for timing, cost, and compliance.
A considered approach at the outset can help explorers avoid unnecessary delays and ensure their exploration program aligns with statutory requirements.