What are the Updated Performance Expectations for Councils under the Statement of Expectations Order 2026 (NSW)

The Environmental Planning and Assessment (Statement of Expectations) Order 2026 commenced on 1 July 2026, establishing a more detailed framework of Ministerial expectations for how councils perform key planning and development functions under the Environmental Planning and Assessment Act 1979.

For NSW mining, resources and development proponents, the changes are particularly relevant because they introduce clearer performance benchmarks and progressively tighter timeframes across development assessment, modifications, planning proposals and strategic planning.

Key expectations include:

🔹 Development applications

Councils should lodge DAs within an average of 7 days of submission, with an adequacy review and invoice expected within 4 days. Internal referrals should be completed within 21 days.

Determination timeframes are also being progressively reduced:

• 90 days — 1 July 2026 to 30 June 2027

• 80 days — 1 July 2027 to 30 June 2028

• 65 days — from 1 July 2028 onwards.

For Regionally Significant Development, Local Planning Panels are expected to determine applications within an average of 20 days after the council finalises its assessment report.

🔹 Modification applications

The Order introduces specific expectations for modification applications.

Section 4.55(1) applications (Modifications involving minor error, misdescription or miscalculations or of no environmental impact) should be determined within 14 days of lodgement. If they are not determined within that period, the application cannot be refused.

For other modification applications, the benchmarks progressively tighten:

s4.55(1A) applications (Modifications involving minimal environmental impact):

65 days → 55 days → 40 days

s4.55(2) applications (Other modifications):

85 days → 75 days → 70 days

with the reductions applying from 2026, 2027 and 2028 respectively.

🔹 Complying Development Variation Statements

Refusals of Complying Development Variation Certificates should be limited to circumstances where the proposed variation is assessed as having significant additional adverse impacts.

🔹 Local infrastructure contributions

Councils should review infrastructure contribution plans at least every 5 years, ensuring work schedules, delivery timeframes and growth and development assumptions remain current.

For councils other than rural or large rural councils, there is also an expectation that at least 20% of available infrastructure contribution funds will be spent annually, averaged over the preceding five years.

Why does this matter?

The Order is significant because council performance is now expressly identified as a consideration when determining whether intervention under section 9.6 of the EP&A Act may be appropriate.

For proponents, the broader direction is one of greater transparency, measurable performance and progressively tighter planning timeframes.

For mining and resources projects, where planning approvals can be a critical component of project delivery, understanding these expectations—and monitoring application progress against the relevant benchmarks—will become increasingly important.

The practical takeaway: the 2026 Order sets a clearer performance framework for councils and signals a continued focus on making NSW planning processes more timely, accountable and outcomes-focused.

Disclaimer

Integrity Tenements provides consulting services only and does not provide legal services. Our consulting services do not constitute legal services nor legal advice and are not provided by Australian legal practitioners acting in that capacity. The laws and regulations which govern the provision of legal services in the relevant jurisdiction do not apply to the provision of non-legal services.