Fast-Tracking Tenements: How the Expedited Procedure Works (and Where It Doesn’t)
What is the expedited procedure?
The expedited procedure is a fast-track process for certain future acts attracting the right to negotiate (“RTN”) process in the Native Title Act 1993 (CTH) (“NTA”) (usually the grant of exploration/retention/prospecting tenements) that the relevant government party considers will have minimal impact on native title under s237 of the NTA.
S237 of the NTA - Act attracting the expedited procedure
A future act is an act attracting the expedited procedure if:
(a) the act is not likely to interfere directly with the carrying on of the community or social activities of the persons who are the holders of native title in relation to the land or waters concerned; and
(b) the act is not likely to interfere with areas or sites of particular significance, in accordance with their traditions, to the persons who are the holders of the native title in relation to the land or waters concerned; and
(c) the act is not likely to involve major disturbance to any land or waters concerned or create rights whose exercise is likely to involve major disturbance to any land or waters concerned.
Under this process, the department must give notice in accordance with section 29 of the NTA of its intention to do future acts. These notices may include a statement, made under section 29(7) of the NTA, that the department considers that the proposed future act attracts the expedited procedure (”the expedited statement”) and that, unless a native title party objects within the notice period, the full RTN process will not apply to the relevant grant.
If no objection is lodged within the notice period, the tenement will usually proceed to grant without further actions. However, if a native title party objects, the NNTT must determine whether the act does in fact attract the expedited procedure.
Does Expedited Process Apply in All Australia Jurisdictions?
The short answer is a No.
Each state and territory has developed their own approach to ensure the validity of the grant of exploration tenement. The most common ones are the RTN process and Indigenous Land Use Agreement (“ILUA”), and we have prepared below a brief summary of the applicable native title pathways for all Australia jurisdictions with comments for clarity.
Comments:
* Expedited procedure is not applicable in NSW, however, the applicant can choose to apply for a low impact exploration licence (“LIEL”) of which the application process resembles the process of expedited procedure. For further information on LIEL, check out our previous article here.
** In QLD, the Department usually processes an application under the expedited procedure if native title protection conditions (”NTPCs”) are imposed on the tenements. The NTPCs are comprehensive and identify the native title parties the tenement holder must engage, what parties must do before and during any exploration and what happens when parties don't meet specified time frames. For further information, check out Version 10.1 of the NTPCs released recently in March 2026 here.
*** In VIC, the Traditional Owner Settlement Act 2010 (Vic) provides the Land Use Activity Agreement (”LUAA”) as an alternative to address native title. The LUAA sets out procedures for undertaking “land use activities” (a practical substitute for the term future acts) and the applicant can opt in the standard terms of the LUAA to avoid complex negotiations. For further information, check out our previous post here.
**** The WA Department’s Guideline - Expedited Procedure Case Management came into effect in 2026 and introduced a new early risk assessment and triage process to identify applications for tenements that are at a high risk of not being able to proceed under the expedited procedure and implemented a case management approach as soon as possible after the receipt of applications. For further details, check out the Guideline here.
***** In SA, exploration tenement holders can comply with the provisions of Part 9B of the Mining Act 1971 (SA) as an alternative by entering into a native title mining agreement (“Part 9B agreement”) before starting any operations on land subject to native title. The Part 9B agreement is usually non-standard, and if it is not reached within the relevant period (six months), any party to the negotiations or the Minister may apply to the ERD Court for a determination.
Any questions in relation to fast-tracking your tenement applications? Contact integritytenements@gmail.com for a confidential chat.
Disclaimer
Integrity Tenements provides consulting services only and does not provide legal services. Our consulting services do not constitute legal services nor legal advice and are not provided by Australian legal practitioners acting in that capacity. The laws and regulations which govern the provision of legal services in the relevant jurisdiction do not apply to the provision of non-legal services.